Construction

Reconstruct/Rehabilitate Transient Apron and Taxiway A

Construction will begin October 16th and is estimated to end January 11th.  The work will be completed in 6 phases. 

 

  • Phase 1 consists of the reconstruction of a portion of Taxiway A and the crack seal and seal coat of the North Tie Down.  The approximate dates of Phase 1 will be October 16th – October 27th .

 

  • Phase 2 consists of the reconstruction of a large portion Taxiway D south of the Transient ramp.  A temporary taxiway will be put in place north of Taxiway D.  The approximate dates of Phase 2 will be October 30th – November 20th.   

 

  • Phase 3 consists of the reconstruction to the east end of taxiway D and a portion of Taxiway A.  This phase also includes the crack seal and seal coat of Taxiway A, south of the existing Fuel Farm.  During this time Runway 27-9 will be closed to departures, and only open for arrivals.  The approximate dates of Phase 3 will be November 13th – November 20th. 

 

  • Phase 4 consists of the reconstruction of the eastern half of the Transient Ramp west of Taxiway A and north of Taxiway D.  The approximate dates of Phase 4 will be November 21st – December 12th.

 

  • Phase 5 consists of the reconstruction of the western half of the Transient Ramp north of Taxiway D and to the east side of the City Ramp.  The approximate dates of Phase 5 are December 13th – January 4th. 

 

  • Phase 6 consists of the crack seal and seal coat of the City ramp and the section of Taxiway D located adjacent to the City Apron.  The work on Taxiway D should be completed overnight and not impact operations during the day.  The approximate dates of Phase 6 are January 4th – January 11th.               

 

Please check NOTAMS to view any closure of pavement at the airport.  The construction plans can be found below and contain more detailed information about the project.  

Reconstruct/Rehabilitate Transient Apron and Taxiway A Phasing